Rs 151-Crore Shillong Ropeway Project Faces Opposition In Meghalaya: What's The Controversy?
A proposed Rs 151-crore ropeway project at Shillong Peak has sparked a dispute between the Meghalaya government, the Khasi Hills Autonomous District Council (KHADC) and local residents, with concerns over its environment
Ni Shuddhanta Patra··170K nabasa
Rs 151-Crore Shillong Ropeway Project Faces Opposition In Meghalaya: What's The Controversy?
A proposed Rs 151-crore ropeway project at Shillong Peak has sparked a dispute between the Meghalaya government, the Khasi Hills Autonomous District Council (KHADC) and local residents, with concerns over its environmental impact and the legality of work at the site.
The project, proposed at Lum Shyllong, has faced opposition from the Voice of the People’s Party (VPP), the KHADC and citizens. The Joint Action Committee (JAC) Against the Shillong Ropeway Project is leading the protests, arguing that construction could threaten water sources, forest cover, wildlife habitats and the area’s fragile ecosystem.
While the committee wants the project to be scrapped or relocated, VPP chief Ardent Miller Basaiawmoit has warned that his party may initiate contempt of court proceedings over alleged violations of a Supreme Court judgment.
Why Did KHADC Seal The Project Site?
The KHADC Enforcement Wing, led by Inspector Kordor Synrem, sealed the lower terminal site on October 27. It also removed project staff and seized materials related to the work, citing alleged violations of the United Khasi-Jaintia Hills District (Trading by Non-Tribals) Regulation, 1954.
The council alleged that the joint venture executing the project, comprising KEC International and Tantia Construction, had started work without obtaining a mandatory trading licence.
The Meghalaya government, however, has opposed the action and asked the KHADC to remove the locks and seals, return the seized materials and give written assurance that the project would not face further action. The Tourism Department also filed a police complaint against KHADC inspector Kordor Synrem. No arrests have been made so far.
In a communication dated October 30 to the KHADC executive committee, the Tourism Department maintained that the premises belonged to the state government and were being used only for preliminary preparations, not construction or commercial activity.
Invoking Section 30(2) of the Meghalaya Ropeway Act, 2022, Tourism Department Commissioner RM Kurbah said promoters could undertake preparatory work before completing the contractor’s licensing formalities.
“The premises of the camp belong to the government. It is a government asset. Therefore, the sealing of the site for the Lower Terminal Point cannot be taken up,” she said.
The department also referred to the Stage-II approval granted by the Ministry of Environment, Forest and Climate Change on October 24, 2024, for diverting 2.3257 hectares of forest land in Riat Laban Reserve Forest and Riat Laban Forest.
VPP Threatens Contempt Of Court Proceedings
Basaiawmoit has backed the protesting residents of Laban Pyllun and questioned the Tourism Department’s decision to file a case against the KHADC inspector.
Defending Synrem, he said, “The officer’s concern was just performing his duty as an officer of the Khasi Hills Autonomous District Council.”
Citing the United Khasi-Jaintia Hills District Management and Control of Forest Act, 1958, the VPP chief argued that Raid forests should be managed by their respective heads under district council rules.
He further alleged that the Tourism Department, Forest Department and leaders of Raid Laban were violating a Supreme Court judgment.
“Therefore, as a party, we may be compelled to file a petition against all the departments, especially the tourism department, for the contempt of court,” he warned.
Why Are Residents Opposing The Ropeway?
The JAC recently walked out of a meeting convened by the government after the Tourism Department made a presentation on the project’s impact on the Lum Shyllong catchment.
In a 10-point submission, the committee repeated its demand to scrap or relocate the project. It also questioned the validity of the 2022 public hearing and sought the cancellation of sanads issued to Rangbah Shnongs allegedly involved in the project.
The government, meanwhile, says the ropeway will improve access to Shillong Viewpoint near Shillong Peak, where visitor movement on the existing road is restricted due to security arrangements. It has also cited reduced traffic congestion and employment generation as expected benefits.
The government has further maintained that the proposed ropeway alignment will not affect the Umiew catchment, which supplies water to the Greater Shillong Water Supply Scheme.