Waiting For Bengaluru’s Pink Line? Not Yet — 36 Safety Fixes Still Pending Before It Opens
Bengaluru’s Pink Line opening hinges on 36 fixes. The Commissioner of Metro Railway Safety has flagged missing fire safety arrangements, malfunctioning lifts, damaged electrical earthing and pending train tests on the Ka
By Afreen Hussain56K reads

Bengaluru’s Pink Line opening hinges on 36 fixes. The Commissioner of Metro Railway Safety has flagged missing fire safety arrangements, malfunctioning lifts, damaged electrical earthing and pending train tests on the Kalena Agrahara–Tavarekere stretch. BMRCL says it will respond within a day or two, but no opening date is out.
In a letter dated October 9, the CMRS, Southern Circle, asked the Bangalore Metro Rail Corporation Ltd (BMRCL) to submit compliance reports and additional technical documents before the section can be authorised for passenger traffic.