The National Grid Corporation of the Philippines (NGCP) announced that the Visayas Grid is under extended red alert status on Tuesday afternoon.
As of August 11 2026, at 1:30 p.m. the Visayas Grid is placed under extended red alert status from 3 p.m. up to 8 p.m.
The same Grid is under yellow alert status from 1 p.m. to 3 p.m. and from 8 p.m. to 10 p.m. with available capacity of 2,123MW and peak demand at 2,418MW.
The NGCP also said eight plants are on forced outage on August 2026, two plants since July, three plants since June, seven plants since May, one plant since March, three plants since 2025, two plants since 2024, two plants since 2023, and one plant since 2021.