The expected cost of the Gateshead Flyover demolition has passed £32m, almost double initial estimates.
The concrete structure was closed in December 2024 due to fears it could collapse, with a six-month demolition completed on 1 October.
Gateshead Council initially set aside £18m for the works, but figures due to be presented next week estimate a total of £32.6m with the possibility of further change, the Local Democracy Reporting Service said.
A council spokesperson said the final overall cost of the project was expected to be confirmed in Spring 2027 once all remaining works had been completed.