Microsoft has reportedly withdrawn from a major data centre agreement with British AI infrastructure company Nscale, dealing a setback to its plans to expand computing capacity in the UK. The proposed facility in Loughton, Essex, was expected to become operational next year, but persistent delays in securing electricity connections have cast doubt on the project’s timeline.
According to The Telegraph, electricity grid operators have indicated that sufficient power may not be available until the 2030s. Microsoft had agreed to lease 23,000 Nvidia AI chips at the site, with the company expected to serve as its anchor tenant.