All of Tyne and Wear's new fleet of Metro trains are ready for carry passengers, after undergoing thousands of hours of testing.
Stadler, the Swiss train manufacturer, have formally handed over the 46th and final Class 555 to operator Nexus, two months ahead of the target deadline at the end of the year.
The final phase of the £362m project involved 90,000 individual tests across the new fleet, with trains undergoing 22,990 miles (37,000 kilometres) of on-track test runs, alongside the training of 480 employees.